2011
We were awarded multiple packages at the Port Hedland Inner Harbour Project. This included the concrete and detailed earthworks for Car Dumper 5 and the SP1 & SP2 General Civil Works. Further to this we were awarded the civil works for Car Dumper 5 and the Stockyard at Rio Tinto’s Cape Lambert Port B (50mtpa+50mtpa) project.

2012
In 2012 DTMT was awarded its largest ever contract, Car Dumper 6/7 and the Stockyard at the Cape Lambert Port B (353mtpa) Project for Rio Tinto. The project involves more than 67,000 cu m of concrete. Further to this we also commenced concrete works for the Train Loadout at Ore Body 24.

2013
After completing the supply and installation of the concrete foundations, slabs, pedestals, basins and bund walls for the Yarnima Power Station, we were also awarded the NGI works. This included the Raw & Treated Water System, Water Treatment Plant Building, Fire Services, and Process Waste Water System.

2014
DTMT was awarded major civil works at FMG's Northstar Project, Rio Tinto's West Angelas Deposit B Project and the Mesa J Sizing Plant. Further to this DTMT completed the NPI Facilities Earthworks at the Cape Lambert B Port B (50MTPA+50MTPA)Project as part of a joint venture with 100% Aboriginal owned, Hicks Civil and Mining.