First Wall Lift Concrete Pour at CD5

Date Published: 10/02/2012

The DTMT and Hanson team have successfully completed the first wall lift concrete pour at the Car Dumper 5 Project located at Finucane Island.

The pour was completed on the 7th and 8th of February. With the aide of three concrete boom pumps, the total concrete placed came to over 1100m³.

The next stage in the CD5 construction is the apron feeder slab followed by the second wall lift.